How to calculate Schedule variance
The Schedule variance formula, with plain worked examples you can check yourself.
Schedule variance = EV − PV
Worked examples
EV = 700 · PV = 600Schedule variance = 100
EV = 950 · PV = 800Schedule variance = 150
EV = 450 · PV = 400Schedule variance = 50
How to use it
- Write down the values for each letter in the formula.
- Do the brackets first, then divide or multiply.
- Check the units before you compare results.
- Compare the answer with last period or with a competitor to see if it is good or bad.